14 RCMP detachments across rural Manitoba reached out to us looking to upgrade their communications towers. The challenge we were facing was the demolition of the existing concrete pads, which needed to be done in order to install the piles. Our solution was to use a custom reaction frame, we were able to span directly over the existing pads, effectively eliminating their demolition.The reaction frame greatly reduced the bending moment forces. This allowed us to use much smaller and more economically friendly piles. The use of much smaller piles further increased the savings for our client by making mobilization to 14 rural Manitoba detachments exponentially more efficient.

 